Remove an edge with DELETE on its TaskDependency row: revive restores its type and offset. A remove on upstream_tasks or downstream_tasks erases the row for good.

API

Q Which call removes one dependency between two Tasks, what does that do to the downstream Task's dates, pinned and dependency_violation, and can the edge be revived with its dependency_type and offset_days, or must it be re-created?

Endpoint DELETE /entity/task_dependencies/<id> ; PUT /entity/tasks/<id> ; POST /entity/task_dependencies/<id>?revive=1 ; POST /entity/task_dependencies ; POST /entity/task_dependencies/_search

Provisioned by the probe, no operator step: it makes the Shot, the Tasks and every edge, and deletes them; a read-back after the run finds no Task, Shot or live TaskDependency row left.

Docs claim Silent. The schema lists upstream_tasks and downstream_tasks as editable multi_entity fields and says nothing about the rows behind them.

Actual

Task fields with valid_types Task: upstream_tasks, downstream_tasks (multi_entity, editable); sibling_tasks (not editable)
late control: u2 03-02..03-06; l1..l4 written 03-23..03-24, l2 and l4 PUT pinned=true, then each edge POSTed
  l1 finish-to-finish +1          -> 03-06..03-09 pinned=False violation=False   (pulled back)
  l2 finish-to-finish +1          -> 03-23..03-24 pinned=True  violation=False
  l3 finish-to-start-next-day +2  -> 03-11..03-12 pinned=False violation=False   (pulled back)
  l4 finish-to-start-next-day +2  -> 03-23..03-24 pinned=True  violation=False
up 03-02..03-06; d finish-to-finish +1, g finish-to-start-next-day +2, e start-to-start +1, f finish-to-start-next-day +2
d written 02-23..02-24 -> pinned=True violation=True       g 03-11..03-12  e 03-03..03-04  f 03-11..03-12
remove  DELETE row d -> 204, DELETE row g -> 204
        PUT e {"upstream_tasks": {"multi_entity_update_mode": "remove", "value": [up]}} -> 200
        PUT up {"downstream_tasks": {"multi_entity_update_mode": "remove", "value": [f]}} -> 200
        GET all four rows -> 404;  _search return_only retired: [(d, finish-to-finish, 1), (g, finish-to-start-next-day, 2)]
        d 02-23..02-24 pinned=True violation=False   g, e, f dates unchanged
PUT up due 03-13 -> d, g, e, f unchanged
revive  POST row d ?revive=1 -> 200 {"did_revive": true}   row g -> the same
        row e, row f -> 404 "Entity of type [TaskDependency] with id=<id> does not exist."
        rows read back: (finish-to-finish, 1), (finish-to-start-next-day, 2), same ids
        d 02-23..02-24 pinned=True violation=True     g 03-18..03-19 (rescheduled from up's 03-13)
re-create  DELETE rows d, g again; PUT up due 03-20 while unlinked
        POST row d finish-to-finish +1 -> 201 new id   d 02-23..02-24 pinned=True violation=True
        POST row g finish-to-start-next-day +2 -> 201   g 03-25..03-26
        PUT e upstream_tasks add [up] -> 200: new row (finish-to-start-next-day, None)   e 03-23..03-24
revive g's old row beside its new one -> 400 "Revive failed for [TaskDependency with id=<id>]: Can't unretire
  the entity because a field has a non-unique value for a unique index: sgcu_task_dependencies"

Teaches

remove by the TaskDependency row undo
DELETE /entity/task_dependencies/<id> retired: 404 on GET, listed under return_only: retired POST .../<id>?revive=1, same id, type and offset
a delete request on the row inside _batch retired, the same (probe 103) revive, the same
remove on the downstream Task's upstream_tasks erased: not listed as retired re-create; revive is 404
remove on the upstream Task's downstream_tasks erased, the same re-create; revive is 404
the downstream Task after the edge is removed after revive or re-create
unpinned dates held where the edge put them; no longer follows the upstream rescheduled at once from the upstream's current dates
pinned, in violation dates and pinned held; dependency_violation false dates held; dependency_violation true again
  • Delete the row, not the link. An undo stack that removes an edge by a multi_entity remove cannot bring it back: the row is gone, and re-adding through upstream_tasks writes a new row typed finish-to-start-next-day with no offset. Record the row id and delete it, by DELETE or in _batch.
  • A re-created row with the same type and offset places the Task as the revived row would. The difference is the id, and the retired original then cannot be revived: the pair is unique across live rows, so revive after re-create is the 400 above. Undo by revive, or by re-create, not both.
  • Neither route restores the downstream Task's old dates. An unpinned Task snaps to the edge as measured against the upstream now (probe 085); an undo that wants the old dates writes them, and the start_date write pins the Task (probe 093).
  • An edge places an unpinned Task exactly, not at the earliest: l1 and l3, written late, were pulled back to the edge. A pinned Task placed later than that reads dependency_violation false for both types (l2, l4); only one placed earlier (d) reads true.