Writing duration on a dependent Task does not pin it; a start_date write in the same run does. It keeps following the upstream, and a duration write upstream moves it.
Q Does writing duration on a dependent Task pin it, the way a date write does? What happens to
its start_date/due_date, and does it still follow the upstream afterwards? Does writing duration
on the upstream Task move its downstream Tasks?
Endpoint PUT /entity/tasks/<id> ; POST /entity/tasks/_search
Docs claim Silent, as for every scheduling field. entity_types/Task and probe 087 cover date
writes on both ends of a chain; probe 093 covers nulling a dependent's dates. Neither writes duration
alone.
Actual
The probe provisions everything: one Shot, four Tasks, two TaskDependency rows, all deleted on exit (read back: 0 Tasks, 0 Shots, 0 live TaskDependency rows).
up -FS-> down -FS-> down2; solo has no edge; every Task written 2026-03-02..03-03 (dur=960)
linked up 03-02..03-03 down 03-04..03-05 down2 03-06..03-09 solo 03-02..03-03
PUT solo duration=1920 (no edges) -> 200 solo 03-02..03-05 dur=1920 pinned=False; chain unchanged
PUT down duration=1920 (dates left alone) -> 200
up 03-02..03-03 down 03-04..03-09 dur=1920 down2 03-10..03-11 pinned=False
PUT up due_date=03-10 (later) -> 200
up 03-02..03-10 down 03-11..03-16 dur=1920 down2 03-17..03-18 pinned=False
PUT down pinned=false (already false) -> 200, nothing changed
PUT up duration=2880 (upstream) -> 200
up 03-02..03-09 down 03-10..03-13 dur=1920 down2 03-16..03-17 pinned=False
PUT down start_date=03-20 (control) -> 200
up 03-02..03-09 down 03-20..03-25 dur=1920 pinned=True down2 03-26..03-27
violation=False on every Task at every step
Teaches
| write | effect on the dependent (down) |
|---|---|
duration alone on an unlinked Task (solo) |
pinned stays false; start_date kept, due_date stretches to hold the new duration |
duration alone on down |
the same: pinned stays false, start_date kept (already the day after the upstream ends), due_date stretches |
| upstream moves later, after that | down moves with it, duration held at 1920 |
duration on the upstream (up) |
up's due_date moves; down and down2 follow it, same as a date write (087) |
start_date on down (control) |
pinned turns true; duration held, due_date moves; down2 follows |
durationdoes not pin. In the same run astart_datewrite ondowndid.due_datewas not written on the dependent here; that it pins too rests onentity_types/Task, 087 and 093.- On the dependent, a
durationwrite keepsstart_dateand movesdue_date, the same as on the unlinkedsolo. The dependent then keeps following its upstream. down2moved on every write that moveddown, theduration-only write included: a dependent's owndurationwrite cascades downstream. It stayed put on the no-oppinned=falsewrite, where nothing moved.- Writing
durationon the upstream end reschedules every unpinned downstream Task, so probe 087's date-based finding holds fordurationtoo.